How to Size a Diesel Generator for an Industrial Site (kVA Calculation Guide)

A step-by-step method for sizing an industrial diesel generator: build a load list, convert kW to kVA, plan for motor starting and step loads, apply site derating and choose between standby, prime and continuous ratings.

An undersized generator trips every time the crusher or compressor starts. An oversized one runs lightly loaded for years, wastes fuel and builds up carbon in the engine. Good diesel generator sizing lands between those two failures, and it starts with your loads, not with a catalogue.

This guide walks through the method site engineers use: list every load, convert power figures into kVA, size for the worst motor start rather than the average, correct for altitude and temperature, and then pick the right duty rating. A worked example ties the steps together.

For the full range of gensets, alternators and related equipment, see our power solutions section. The method below applies whether you are powering a quarry, a construction camp, a factory with no reliable grid, or standby supply for a plant.

Step 1: Build a load list before you talk about kVA

Every reliable sizing exercise starts with a load schedule. Walk the site, or the single-line diagram, and record each item that the generator will feed. Skipping this step and guessing a round number is the most common cause of generator problems.

What to record for each load

  • Name and quantity, for example three conveyor motors.
  • Rated power in kW, or voltage and full-load current if only the nameplate amps are known.
  • Power factor, where it is stated on the nameplate.
  • Starting method for motors: direct-on-line, star-delta, soft starter or variable frequency drive.
  • Load type: motor, resistive heating, lighting, electronics, welding, or non-linear loads such as drives and UPS systems.
  • Duty pattern: running continuously, cycling, or used only occasionally.

Then decide which loads run together. A workshop may have many machines installed, but a realistic peak might be the compressor, two conveyors, the lighting and the site office at once. Applying a diversity judgment here is legitimate, provided it is based on how the site really operates and not on wishful thinking.

Plan for growth as well. If a second crusher line or a larger compressor is likely within a few years, it is usually cheaper to size for it now than to parallel a second set later. Note any future loads separately so that the decision stays visible.

Step 2: Convert kW to kVA and understand power factor

Generators are rated in kVA because the alternator and its windings must carry the full current, whether that current does useful work or not. Engines, on the other hand, deliver kW. The link between the two is power factor.

The basic formulas

  • kW = kVA × power factor. Most industrial generator sets are rated at a power factor of 0.8, so a 500 kVA set corresponds to roughly 400 kW of engine output.
  • Three-phase kVA = √3 × voltage × current ÷ 1,000. Use this when you only have line voltage and current from the nameplate or a clamp meter.
  • Single-phase kVA = voltage × current ÷ 1,000.

Add up the running kW of everything that operates together, then convert to kVA using the combined power factor. If your loads are mostly induction motors, the site power factor is often in the region of 0.8 to 0.85. If it falls well below 0.8, the alternator may become the limit before the engine does, and correction or a larger alternator should be discussed.

Non-linear loads

Variable frequency drives, rectifiers, UPS units and LED drivers draw distorted current. This creates extra heating in the alternator and can upset the voltage regulator. Where these loads form a large share of the total, generator suppliers commonly recommend an oversized alternator or a permanent-magnet excitation system. Tell the supplier the proportion of non-linear load so it can be checked.

/ Free PDF checklist

Diesel Generator Sizing – Site Data Checklist

12 points to settle before you request quotes – print it or send it back to us filled in.

We use your email only to send related information. No spam.

Step 3: Size for motor starting and step loads

The running load tells you the minimum size. The largest motor start often decides the real size. When an induction motor starts direct-on-line, it typically draws several times its full-load current, often in the range of six to eight times, until it reaches speed. The generator sees that as a sudden demand for kVA at low power factor.

If the set cannot supply it, voltage dips sharply. Contactors drop out, lights flicker, electronics reset and, in the worst case, the motor stalls. Generator suppliers check starting performance against an acceptable voltage dip, often somewhere around 15–20% for general industrial loads, though sensitive equipment may need less.

Ways to reduce the starting burden

  • Star-delta starting cuts starting current to roughly a third of the direct-on-line value.
  • Soft starters commonly limit current to around two to four times full-load current.
  • Variable frequency drives can bring starting current close to running current, but add non-linear load.
  • Sequencing starts the largest motor first, while the generator is lightly loaded, then adds the rest in steps.

Air compressors deserve special attention because they are frequently the largest motor on a quarry or workshop site. Machines such as oil-cooled screw air compressors often come with star-delta or soft-start options, and choosing one can reduce the generator size you need. Our screw vs piston compressor guide covers duty cycles in more detail.

Step 4: Choose standby, prime or continuous rating

The same engine and alternator can carry different nameplate figures depending on how it will be used. The ratings are defined in ISO 8528-1, and suppliers’ data sheets usually quote at least two of them.

The three ratings in plain terms

  • Standby (emergency standby power): for supplying a variable load during a grid outage, with limited annual running hours and no overload allowance. This is the highest figure on the data sheet.
  • Prime power: for supplying a variable load for unlimited hours where the generator is the main source, with a short overload capability. Prime ratings are typically around 10% lower than standby on the same set.
  • Continuous power: for supplying a constant load for unlimited hours, such as base load in parallel with other sets. This is the most conservative figure.

A remote quarry or construction site with no grid needs a prime rating. A factory that only runs the set when the utility fails can use standby. Sizing a site’s main supply on a standby figure is a frequent and costly mistake, because the set will be overloaded by its own definition.

Target loading

Diesel engines tend to run best when they carry a substantial share of their rating. Many engineers aim for an average load of roughly 60–80% of the prime rating. Running for long periods below about 30% load can cause wet stacking, where unburned fuel and carbon build up in the exhaust. If loads vary a lot, two smaller sets in parallel may suit better than one large set.

Generator duty ratings at a glance (general definitions, ISO 8528-1)
FactorStandbyPrimeContinuous
Typical useBackup during grid outagesMain power on off-grid sitesConstant base load
Annual running hoursLimitedUnlimitedUnlimited
Load profileVariableVariableConstant
Overload allowanceNoneShort-term overload usually allowedNone
Relative nameplate figureHighestTypically about 10% below standbyLowest
Common mistakeUsing it to size a site's main supplyIgnoring motor startingOver-specifying for variable loads

Step 5: Correct for altitude, heat and enclosure

A generator’s output is stated at reference conditions. Real sites are often higher, hotter or dustier. Thinner air at altitude and hot intake air both reduce the oxygen available for combustion, so the engine produces less power, and the cooling system has less margin.

Each engine has its own derating curve, usually starting somewhere above about 1,000 m altitude and above an ambient temperature of roughly 25–40 °C, depending on the model. Ask for the curve for the exact engine and apply it to your highest site altitude and hottest expected ambient, not the average.

Other site factors

  • Enclosures: a silent diesel generator canopy reduces noise but can raise intake temperature if ventilation is tight. Check that the canopy is rated for your ambient.
  • Containerised sets: a container diesel generator suits large outputs and harsh sites, but the air path and radiator capacity still need checking.
  • Dust: quarries and cement plants often need heavy-duty air filtration.
  • Fuel quality: high-sulphur or contaminated fuel affects engine choice and service intervals.
  • Voltage and frequency: confirm 50 or 60 Hz and the site voltage before quoting, since changing frequency changes output.

Write all of these into your enquiry. A supplier can only size around conditions it has been told about.

A worked example: small quarry site

The figures below are illustrative arithmetic to show the method, not a recommendation for a particular site.

Assume a quarry runs a 110 kW jaw crusher motor, a 75 kW screw compressor, two 15 kW conveyor motors, and 20 kW of lighting, pumps and office load, all at 400 V, 50 Hz.

  1. Running load: 110 + 75 + 15 + 15 + 20 = 235 kW.
  2. Convert to kVA: at a combined power factor of 0.8, that is about 294 kVA.
  3. Starting check: the crusher is the largest motor. With a soft starter limiting current to around three times full load, its starting demand is far lower than a direct-on-line start would be. The supplier would model this against the alternator’s motor-starting curve and the allowed voltage dip.
  4. Sequence: start the crusher first, then the compressor, then conveyors and auxiliaries.
  5. Loading target: to keep average load near 70–80% of prime, a prime rating somewhere around 350–400 kVA would be a sensible starting point for discussion.
  6. Derating: if the quarry sits at 1,800 m and sees 45 °C in summer, apply the engine’s derating curve, which may push the selection up a size.

The result is a shortlist, not a final answer. Starting performance, alternator size and fuel consumption should be confirmed with the supplier’s data for the specific set, such as a construction diesel generator configured for site use.

Frequently asked questions

How do I convert kW to kVA for a generator?

Divide kW by the power factor. Most industrial gensets are rated at a power factor of 0.8, so 400 kW of load needs about 500 kVA. If you only know voltage and current on a three-phase supply, kVA equals 1.732 × volts × amps ÷ 1,000. Use the combined power factor of the loads that run together, not a single machine’s figure.

How much bigger than my load should the generator be?

There is no single multiplier. The set must cover the running load, the worst motor start within an acceptable voltage dip, site derating and planned growth. Many engineers aim for an average running load of roughly 60–80% of the prime rating. Going far beyond that increases cost and risks running the engine too lightly.

What happens if a diesel generator is oversized?

Long periods at low load, often below about 30% of rating, can cause wet stacking: unburned fuel and carbon collect in the exhaust and cylinders. Fuel consumption per kWh also rises. If your load varies widely, consider two smaller sets in parallel or a load bank for periodic exercise rather than one large set.

Can I use the standby rating for a remote site?

No. Standby ratings are defined for emergency use with limited annual hours and no overload allowance. A site where the generator is the only source of power should be sized on the prime rating. Using standby figures for a prime application overloads the set by definition and shortens engine life.

Does a soft starter really reduce the generator size?

Often, yes. A direct-on-line motor start commonly draws six to eight times full-load current, while a soft starter typically limits it to around two to four times. That lowers the kVA surge and voltage dip, which may allow a smaller set. The supplier should confirm with the alternator’s motor-starting data for your largest motor.

Next step

Size a generator from a real load list: convert to kVA, check the largest motor start, choose the right duty rating and apply derating for your site. Send that data with your enquiry and our engineers in Shanghai can help shortlist suitable diesel generator sets and matching screw air compressors. When your load list is ready, request a quote and we will state price, lead time and shipping for each option.